Description/Review |
Projects that create an acre or more of earth disturbance require a permit from the Agency’s Stormwater Program. Construction activities are reviewed to ensure projects do not cause water quality impacts and implement adequate erosion prevention and sediment control (EPSC) practices. |
ANR Atlas Layers |
Stormwater Permits (Issued & Pending) |
ANR Technical Program |
|
Criterion Specific Site Plan Information |
Limits of earth disturbance, total earth disturbance square feet, erosion protection and sediment control measures, topographic lines |
Criterion Specific Narrative Information |
Describe EPSC measures. Describe whether project is part of common plan of development. Acreage of disturbance |
Policy/Guidance Documents & Rules |
|
ANR Permits/Approvals |
Construction Stormwater Permit, Multi-Sector General Permit, or confirmation from DEC Stormwater Program no permit is required |